TEL3 FDAS Project Phases
Phase 1 : Initial Checkup of Electrical System of FDAS Date Started : Scope of Work : Findings : Some detectors are unpowered hence to move forward in the checking and testing of the other detectors the lack of power must be addressed first. Completion Report? Phase 2 : Addressing the No-Power Issues of detectors Date Started : Scope of Work : Findings : As power lines have been corrected to be able to power up the detectors if was found out that the original and sole power booster is not enough to power all the now active detectors. Proposed Correction : Additional Power Boosters Completion Report? Phase 3 : Addressing the Bad System Design with Additional Power Boosters Date Started : Scope of Work : Findings : As additional power boosters provided enough power to the detectors troubles are now reported by the FDAS panel and have to be addressed one by one Proposed Correction : Preventive Maintenance Completion Report? Phase 4 : Preventive Maintenance (ongoing)...